60.
Which of the following is not included in SRS?
a.
Performance
b.
Functionality
c.
Design solutions
d.
External Interfaces
Answer:
Option (c)
61.
The main goal of arriving at a final
specification
is _____?
a.
To compute the cost of implementing the
system
b.
To assist in designing the system
c.
To tell the organization’s managers how
the
system will function
d.
To tell the organization’s
managers
what
the proposed system will achieve
in
a language understood by them
Answer:
Option (d)
62.
Final specifications are drawn up by _____?
a.
System designers along with users
b.
The managers of user organization
c.
System analyst in consultation with
programmers
d.
System analyst in consultation with the
management
of the organization
Answer:
Option (d)
63.
The role of a system analyst drawing up a
requirements
specification is similar to _____?
a.
Architect designing a building
b.
A structural engineer designing a building
c.
A contractor constructing a building
d.
The workers who construct a building
Answer:
Option (a)
64.
Which one from the following is highly
associated
activity of project planning?
a.
Keep track of the project
b.
Compare actual and planned progress and
costs
c.
Identify the activities, milestones and
deliverables
produced by a project
d.
Both B and C
Answer:
Option (c)
65.
The final specifications are arrived at _____?
a.
During feasibility study
b.
After feasibility study
c.
Just before implementation phase
d.
When the system is being designed
Answer:
Option (b)
66.
Arrange the given sequence to form a SRS
prototype
outline as per SRS standard.
i).
General description
ii).
Introduction
iii).
Review
iv).
Appendices
v).
Specific Requirements
a.
iii, i, ii,v, iv
b.
iii, ii, i, v, iv
c.
ii, i, v, iv, iii
d.
iii, i, ii,v,iv
Answer:
Option (c)
67.
Requirement prioritization and negotiation
belongs
to _____?
a.
Feasibility study
b.
Requirement elicitation
c.
Requirement validation
d.
Requirements reviews
Answer:
Option (b)
68.
System approval criteria are specified _____?
a.
During feasibility study
b.
During the requirements specifications
stage
c.
During system study stage
d.
When the final specifications are drawn
up
Answer:
Option (d)
69.
Which of the following is used to determine the
specificity
of requirements? Where n1 is the
number
of requirements for which all reviewers
have
identical interpretations, n2 is number of
requirements
in a specification.
a.
n1/n2
b.
n2/n1
c.
n1+n2
d.
n1–n2
Answer:
Option (a)
70.
Requirementmanalysis is critical to the success
of
a development project.
a.
True
b.
False
c.
Depends upon the size of project
d.
None of the mentioned
Answer:
Option (a)
71.
How many feasibility studies is conducted in
Requirement
Analysis?
a.
Two
b.
Three
c.
Four
d.
None of the mentioned
Answer:
Option (b)
72.
The statement “Conformity to a standard is
maintained” depicts _____________ property
of
SRS.
a.
Correct
b.
Complete
c.
Consistent
d.
Modifiable
Answer:
Option (b)
73.
The SRS is said to be consistent if and only if
a.
its structure and style are such that any
changes
to the requirements can be made
easily
while retaining the style and
structure
b.
every requirement stated therein is one
that
the software shall meet
c.
every requirement stated therein is
verifiable
d.
no subset of individual requirements
described
in it conflict with each other
Answer:
Option (d)
74.
The SRS document is also known as
_____________
specification.
a.
black-box
b.
white-box
c.
grey-box
d.
none of the mentioned
Answer:
Option (a)
75.
The dynamic behaviour of the system is
represented
by which model?
a.
Context Model
b.
Behavioral Model
c.
Data Model
d.
Object Model
Answer:
Option (b)